Kingborough Sewerage Upgrade

ACCIONA and BMD have been selected by TasWater as the preferred bidder for the design and construction to the existing Blacksman Bay Sewage Treatment Plant which is valued at A$39M.

The existing sewage treatment plant has been operating for 30 years and is at its end of its service life. An upgrade will be needed in order to accommodate the future growth in Kingborough. This upgrade will increase capacity from 4.1 Million Litres per Day to 8.5 Million Litres per Day.

The upgrade to the sewage plant will include construction to earth works, new roadways, new buildings and new tanks as well as equipment installation and commissioning. An Environmental Management Plan will be required before construction in order to evaluate site management, erosion control, air quality, flora and fauna, noise management, and traffic management.

GENERAL INFORMATION

  • Location: Kingborough, Tasmania

  • Our role: Introducing a wastewater treatment process called Intermittently Decanted Extended Aeration (IDEA) which is combined with Sequential Batch Reactor (SBR) technology in order to provide a cost efficient way of treating wastewater.

  • Infrastructure: Kingborough Sewerage System

  • Project Value: A$39M

  • Estimated completion date: 21 months to design and construct

  • Maintenance Period: 24 months of performance evaluation

KEY FEATURES

ACCIONA and BMD will be the delivery contractors for the project with design and construction to the upgrade of the existing Blackmans Bay Sewage Treatment Plant.

  • Current treatment capacity 4.1 Million Litres per Day

  • Increase of treatment capacity to 8.5 Million Litres per Day

  • Construction of a new sewage pipeline to take waste from Margate, Electrona and Howden to the Blackmans Bay Sewage Treatment Plant

  • 21 months to design and construct

 

BENEFITS

  • The Kingborough Sewerage Upgrade Project will introduce a wastewater treatment process called Intermittently Decanted Extended Aeration (IDEA) which will be combined with Sequential Batch Reactor (SBR) technology in order to provide a cost efficient way of treating wastewater

  • Closure of 3 existing and underperforming sewage plants at Electrona, Margate, and North West Bay Golf Club

  • One of the sustainable components of this project will be to treat the wastewater without any chemical dosing, utilising Ultra Violet disinfection instead of chlorine this will help to promote a safe environment for the plant operators and reducing any impacts on the environment

  • This upgrade will improve the existing odour issues at Blackmans Bay and Dru Point (Margate)

  • The construction of the new pipeline known as the Blue pipeline route were considered on community views, environmental consideration, engineering considerations, and lastly on cost and operational efficiency

CURRENT STATUS

ACCIONA and BMD have been selected to lead the design and construction of the Kingborough Sewerage Upgrade Project. Design and construction will take 21 months, and a 24 month performance evaluation period. The project is currently underway.

discover other flagship projects

Kawana STP K150 Upgrade Project

Warana, Sunshine Coast, Queensland (Australia)

ACIONA is the proud process delivery contractor for the project of Unitywater’s Kawana Sewage Treatment Plant and responsible in collaboration with Monadelphous, for the design, construction and maintenance of the AU$56M sewage treatment facility.

Atotonilco Wastewater Treatment Plant

Atotonilco, Hidalgo (Mexico)

The contract includes the construction and subsequent operation of the world's largest waste water treatment plant, located in Atotonilco, in the state of Hidalgo.

Move up

YOU'RE JUST ONE STEP AWAY!

Please, confirm your subscription on the email we have sent you and your registration will be completed.

YOU'VE ONLY GOT ONE STEP LEFT!

Please confirm your subscription in the email we just sent you to complete the registration and you will be able to download your ebook.

YOU ARE ALREADY SUBSCRIBED TO THE NEWSLETTER!

If you've missed our content, try checking your junk mailbox and
add us to your address book so you can enjoy them without any problem.

labelSubscribeError

Your email has been unsubscribed. You will not receive more newsletters, unless you subscribe again. Thank you very much