The Preston Tram Workshops Redevelopment Project involved the full reconstruction of the Preston Tram Workshops. The primary objective and purpose delivered by the project were to successfully upgrade the existing workshops to provide a modern & operationally efficient facility for mixed fleet tram depot operation & maintenance activities that met the requirements of Yarra Trams' Strategic Operations Plan and Tram Cascade Plan.
The Preston facility, one of the largest light rail maintenance facilities in the world, is currently a heavy maintenance and servicing center for Melbourne’s tram fleet.
In the broader redevelopment of the Preston Tram Depot, the project works comprise the redevelopment of approximately 80% of the site, including substantial slab track works outside the property in Miller St, the junction of Miller Street and St Georges Road and in Miller St, High Street and Plenty Road, Preston. The redevelopment project entails a series of coordinated and staged sub-projects, with progressive handover of agreed areas and decanting of existing maintenance and operational functions.
GENERAL INFORMATION
Location: Victoria, Australia
Contract: D&C
Infrastructure: The development of the existing site to facilitate stabling, servicing and maintenance of up to 70 E-class and five C2-class trams planned to be operated from Preston in 2016 whilst accommodating for a range of maintenance, project and workshop activities for other tram types.
Completion date: February 2016
Project Value: AU$190 million
KEY DETAILS
Coleman Rail, an ACCIONA company was appointed as Principle Contractor and was responsible for all facets of project delivery & implementation including design, construction, overseas procurement/importation, installation, testing and commissioning activities.
Coleman Rail was responsible to manage all depot design aspects (1760 drawings split over 70 major design packages), including track, OHLE, electrical, civil and architectural. Coleman Rail also lead a Lean Management Review of the operation of the depot, leading the clients workforce to challenge and refine work practises.
All works involved progressed in a staged manner to facilitate the programmed introduction of E-class trams whilst concurrently accommodating ongoing delivery and off-loading of E-class trams onto the Preston Workshops property. The manner in which the works were conducted to minimise the disruption to heavy maintenance and depot operations meant it was vital to communicate and coordinate interface management and project staging to avoid any delay’s to the Other Works Contractors also.
BENEFITS
CURRENT STATUS
The Preston Workshops Redevelopment Project was successfully completed in February 2016 and serves its intended purpose through a thoroughly planned and well executed scope of works alongside strong management and coordination.
ACCIONA was the lead partner of the Transcity Joint Venture, for the design, construction, operation and 10 year maintenance of the $1.5 billion Legacy Way project, in Brisbane, Queensland.
ACCIONA is the Principal Design and Construct JV partner of the ALTRAC consortium, awarded with the contract to design and construct the $2.1 billion Sydney CBD South East Light Rail.
View ACCIONA Social Networks