Glenelg Tram Line Extension

A high profile project championed by the South Australian Premier, the Glenelg Tramline extension from Victoria Square to the Adelaide Convention Centre was the first major tramway expansion in Adelaide for some time. Passing through sensitive streetscapes with historic buildings, significant commercial buildings and civic buildings, the route runs through Adelaide’s major city streets, King William Street and North Terrace.

General information

Location: Adelaide, Australia

Contract: D&C

Infrastructure: Passing through sensitive streetscapes with historic buildings, significant commercial buildings and civic buildings, the route (1.6 km) runs through Adelaide’s major city streets, King William Street and North Terrace.

Completion date: September 2007

Contract value: AU$22 million

Key Details

Following the successful delivery of the Glenelg Tramline Upgrade, Coleman Rail, an ACCIONA company was selected to design, construct and commission the new 1.6km dual track tramline.

The overall design, construction, commissioning, and driver and operator training were conducted over a 38-week period.

Planning involved considerable consultation and liaison with the Adelaide City Council, hotels, churches and businesses along the route to negotiate traffic management, access and alternative parking arrangements, disruptions and road closures, noise control, and the design treatments of structures and finishes. The D&C Contract included the design and complete reconstruction of:
- 10km of dual track in ballast, including 9 road crossings and the refurbishment of 12 turnouts.

- Passenger facilities including 18 tram stops, with raised platforms and 41 pedestrian crossings both with access mazes and ramps to DDA compliant standards.

- The upgrade of 4 No. 600VDC converter stations, construction of a new traction power side feeder system and modification of the overheads.

- Upgrade of the signalling system.

- Alterations to the maintenance depot to accommodate new light rail vehicles, as well as the old trams, including introduction of retractable overhead maintenance platforms, 600VDC shore supply and an LRV jacking system.

 

Benefits

  • The project further enhanced Coleman Rail’s project planning and project management capabilities.
  • It also exposed a young team of Construction Managers, Project Engineers and Construction Supervisors to a high profile and complex construction project, further developing their skills and capabilities.

 

Current Status

The project was satisfactorily completed within the required timeframe and budget. It received positive political, media and community feedback and exposure. It achieved high levels of satisfaction from the hotels, businesses and churches along the route due to the unexpected short-term inconvenience.

Image Gallery

discover other flagship projects

Legacy Way Tunnel

Brisbane, QLD (Australia)

ACCIONA was the lead partner of the Transcity Joint Venture, for the design, construction, operation and 10 year maintenance of the $1.5 billion Legacy Way project, in Brisbane, Queensland.

Sydney Light Rail

Sydney, NSW (Australia)

ACCIONA is the Principal Design and Construct JV partner of the ALTRAC consortium, awarded with the contract to design and construct the $2.1 billion Sydney CBD South East Light Rail. 

Move up

YOU'RE JUST ONE STEP AWAY!

Please, confirm your subscription on the email we have sent you and your registration will be completed.

YOU'VE ONLY GOT ONE STEP LEFT!

Please confirm your subscription in the email we just sent you to complete the registration and you will be able to download your ebook.

YOU ARE ALREADY SUBSCRIBED TO THE NEWSLETTER!

If you've missed our content, try checking your junk mailbox and
add us to your address book so you can enjoy them without any problem.

labelSubscribeError

Your email has been unsubscribed. You will not receive more newsletters, unless you subscribe again. Thank you very much